On Monday Day 41 the 3 framers started laying out 2nd floor beams and joists. They started off by tearing open celing of dining room and our middle bedroom (shown) to remove existing 2x4 ceiling joists to make way for new 2"x14" LVL beams.
On Tuesday Day 44 they completed framing out the floorplan for the 2nd story, including the cantilever on south side. 2nd story walls should start popping up next. -JM