Framing crew is almost done, a lot of odds and ends at this point. The fix is done for the front left window that was too close to the roof below it. All the roof sheathing is in place. The bldg inspector was out yesterday inspecting the shear walls, and since roof sheathing was already done he approved that as well, which was a nice bonus.
Stucco scaffolding is up. Working with SMUD to get utility moved along the fenceline so we dont have wires across the backyard... week and a half and counting waiting for the beaurocrats.
Rest of the upstairs windows are up. Plumbing mostly done, and electrical boxes and lighting cans are mostly in.